"Where quality is the fabric of everything we do."

Saturday, June 30, 2012

OJT Experience

Kevin Ravago

                        I started my On-the-Job Training on April 10, 2012 at the Monolith Construction and Development Corporation. The on-going project is the Robinson’s Place Magnolia Town Center located at the Aurora Blvd. cor. Dona Hemady St., Quezon City.

                        On my first day of work, the floor that was assigned to me was the 4th & 5th floors where the Go Hotel is located. The work status of the Go Hotel at that time was delayed due to the revision of the layout. The whole structure is already on its finishing stage so I did not witness the structural works. The activities that I was able to observed were waterproofing, concrete rectification and rub concreting at columns, beams and precasts, and also the construction of the formworks up to the concrete pouring of the stairs.



On my first two weeks at the Go Hotel, I was able to witness the wall partitioning by shotcrete pouring. Shotcrete is a mortar or high performance concrete conveyed through a hose and pneumatically projected at high velocity onto a backing surface. The equipment that is used for shotcrete pouring is the Turbosol.

Our engineer-in-charge discussed the process of shotcrete pouring. First, the area must be well cleaned, and then the layout and work permits must be approved. After that, Rebar dowelling or insertion of dowel bars onto the floor up to the top enclosing the wall partition and then styrofoams are placed running onto the dowel bars. And then, installation of reinforcement and hardware cloth is done. The skeletal form of the partition is now ready for “rebokada” or scratch coat. After the scratch coat is completed, shotcrete pouring or the spraying of concrete is applied.





On April 30, 2012, I was transferred to basement 2. My new engineer-in-charge is Engr. Gerick Pascual. On the same day, we were given a specific area/room in our floor where we are tasked to prepare the room for turnover for 7 days. The rooms that were assigned to us are Elevator lobby and MCD room. In this task, we were able to directly supervise the manpower deployed in the rooms with the assistance of Engr. Gerick. The actual work progress of the Elevator lobby and MCD room has met the prepared schedule on time with the cooperation of the leadmen in basement 2.

 I spent three weeks on Basement 2 where I witnessed the application of sealer on floors, the putty, the first coat up to the final coating on parking lots. The final coating of paint on driveway on turning slots are unlike on the parking lots and straight driveways, after the first coat was done, silica sand is being showered on floors and after that the final coating can only be applied. The application of silica sand before the final coat will cause friction on tires when turning.



Through this On-the-Job Training with the help of my engineers-in-charge, Engr. Rowel Gabriel and Engr. Gerick Pascual, I have learned new things and has widen my knowledge in the field of construction. I also value time management where schedules and decision makings are very much important and proper supervision on manpower is required to meet the deadlines. This whole training has helped me in pursuing my plans to have my career in the field of construction.


No comments:

Post a Comment